Multicriteria scheduling problems: a survey

V. T'kindt; J.-C. Billaut

RAIRO - Operations Research (2010)

  • Volume: 35, Issue: 2, page 143-163
  • ISSN: 0399-0559

Abstract

top
This paper presents a state-of-the-art survey on multicriteria scheduling and introduces a definition of a multicriteria scheduling problem. It provides a framework that allows to tackle multicriteria scheduling problems, according to Decision Aid concepts. This problem is decomposed into three different problems. The first problem is about obtaining a model. The second one is how to take criteria into account and the third one is about solving a scheduling problem. An extension to an existing notation for scheduling problems is proposed for multicriteria scheduling problems. Then, basic results from the literature on multicriteria optimization are presented. These results are used to build the final scheduling problem to solve. Finally a survey is presented for one-machine, parallel machines and flowshop multicriteria scheduling problems.

How to cite

top

T'kindt, V., and Billaut, J.-C.. "Multicriteria scheduling problems: a survey." RAIRO - Operations Research 35.2 (2010): 143-163. <http://eudml.org/doc/116593>.

@article{Tkindt2010,
abstract = { This paper presents a state-of-the-art survey on multicriteria scheduling and introduces a definition of a multicriteria scheduling problem. It provides a framework that allows to tackle multicriteria scheduling problems, according to Decision Aid concepts. This problem is decomposed into three different problems. The first problem is about obtaining a model. The second one is how to take criteria into account and the third one is about solving a scheduling problem. An extension to an existing notation for scheduling problems is proposed for multicriteria scheduling problems. Then, basic results from the literature on multicriteria optimization are presented. These results are used to build the final scheduling problem to solve. Finally a survey is presented for one-machine, parallel machines and flowshop multicriteria scheduling problems. },
author = {T'kindt, V., Billaut, J.-C.},
journal = {RAIRO - Operations Research},
keywords = { Scheduling; multicriteria optimization; state-of-the-art.; state-of-the-art survey},
language = {eng},
month = {3},
number = {2},
pages = {143-163},
publisher = {EDP Sciences},
title = {Multicriteria scheduling problems: a survey},
url = {http://eudml.org/doc/116593},
volume = {35},
year = {2010},
}

TY - JOUR
AU - T'kindt, V.
AU - Billaut, J.-C.
TI - Multicriteria scheduling problems: a survey
JO - RAIRO - Operations Research
DA - 2010/3//
PB - EDP Sciences
VL - 35
IS - 2
SP - 143
EP - 163
AB - This paper presents a state-of-the-art survey on multicriteria scheduling and introduces a definition of a multicriteria scheduling problem. It provides a framework that allows to tackle multicriteria scheduling problems, according to Decision Aid concepts. This problem is decomposed into three different problems. The first problem is about obtaining a model. The second one is how to take criteria into account and the third one is about solving a scheduling problem. An extension to an existing notation for scheduling problems is proposed for multicriteria scheduling problems. Then, basic results from the literature on multicriteria optimization are presented. These results are used to build the final scheduling problem to solve. Finally a survey is presented for one-machine, parallel machines and flowshop multicriteria scheduling problems.
LA - eng
KW - Scheduling; multicriteria optimization; state-of-the-art.; state-of-the-art survey
UR - http://eudml.org/doc/116593
ER -

References

top
  1. G. Adamopoulos and C. Pappis, Scheduling jobs with different job-dependent earliness and tardiness penalties using the SLK method. Eur. J. Oper. Res.88 (1996) 336-344.  
  2. M. Ahmed and P. Sundararaghavan, Minimizing the weighted sum of late and early completion penalties in a single machine. IEEE Trans.22 (1990) 288-290.  
  3. D. Alcaide, J. Riera and J. Sicilia, An approach to solve bicriterion flow-shop scheduling problems, in Proc. of the 6th International Workshop on Project Management and Scheduling (PMS'98). Istanbul, Turkey (1998) 151-154.  
  4. B. Alidaee and A. Ahmadian, Two parallel machine sequencing problems involving controllable job processing times. Eur. J. Oper. Res.70 (1993) 335-341.  
  5. M. Azizoglu, S.K. Kondakci and M. Koksalan, Bicriteria scheduling: Minimizing flowtime and maximum earliness on a single machine, edited by J. Climaco, Multicriteria Analysis. Springer-Verlag (1997) 279-288.  
  6. M. Azizoglu and S. Webster, Scheduling job families about an unrestricted common due date on a single machine. Internat. J. Production Res.35 (1997) 1321-1330.  
  7. U. Bagchi, Y.-L. Chang and R. Sullivan, Minimizing absolute and squared deviations of completion times with different earliness and tardiness penalties and a common due date. Naval Res. Logist.34 (1987) 739-751.  
  8. U. Bagchi, R. Sullivan and Y.-L. Chang, Minimizing mean absolute deviation of completion times about a common due date. Naval Res. Logist. Quarterly33 (1986) 227-240.  
  9. U. Bagchi, R. Sullivan and Y.-L. Chang, Minimizing mean squared deviation of completion times about a common due date. Management Sci.33 (1987) 894-906.  
  10. S. Bansal, Single machine scheduling to minimize weighted sum of completion times with secondary criterion - a branch and bound approach. Eur. J. Oper. Res.5 (1980) 177-181.  
  11. J. Barnes and L. Vanston, Scheduling jobs with linear delay penalties and sequence dependent setup costs. Oper. Res.29 (1981) 146-160.  
  12. C. Bector, Y. Gupta and M. Gupta, Determination of an optimal common due date and optimal sequence in a single machine job shop. Internat. J. Production Res.26 (1988) 613-628.  
  13. J.-C. Billaut, V. T'kindt, P. Richard and C. Proust, Three exact methods and an efficient heuristic for solving a bicriteria flowshop scheduling problem, in Multiconference on Computational Engineering in Systems Applications (CESA 98), Symposium on Industrial and Manufacturing Systems, IEEE-SMC/IMACS. Nabeul-Hammamet, Tunisia (1998) 371-377.  
  14. J. Blazewicz, K. Ecker, E. Pesch, G. Schmidt and J. Weglarz, Scheduling computer and manufacturing processes. Springer-Verlag (1996).  
  15. V. Bourgade, L. Aguilera, B. Penz and Z. Binder, Problème industriel d'ordonnancement bicritère sur machine unique : modélisation et aide à la décision. APII29 (1995) 331-341.  
  16. V. Bowman, On the relationship of the tchebycheff norm and the efficient frontier of multiple-criteria objectives, edited by H. Thiriez and S. Zionts, Multiple Criteria Decision Making. Springer-Verlag (1976) 76-85.  
  17. R. Burns, Scheduling to minimize the weighted sum of completion times with secondary criteria. Naval Res. Logist. Quarterly23 (1976) 125-129.  
  18. S. Chand and H. Schneeberger, Single machine scheduling to minimize weighted completion time with maximum allowable tardiness, Research report. University of Purdue (1984).  
  19. S. Chand and H. Schneeberger, A note on the single machine scheduling problem with minimum weighted completion time and maximum allowable tardiness. Naval Res. Logist. Quarterly33 (1986) 551-557.  
  20. S. Chand and H. Schneeberger, Single machine scheduling to minimize weighted earliness subject to no tardy jobs. Eur. J. Oper. Res.34 (1988) 221-230.  
  21. C.-L. Chen and R. Bulfin, Scheduling unit processing time jobs on a single machine with multiple criteria. Comput. Oper. Res.17 (1990) 1-7.  
  22. C.-L. Chen and R. Bulfin, Complexity of single machine, multi-criteria scheduling problems. Eur. J. Oper. Res.70 (1993) 115-125.  
  23. C.-L. Chen and R. Bulfin, Complexity of multiple machines, multi-criteria scheduling problems, in 3rd Industrial Engineering Research Conference (IERC'94). Atlanta, USA (1994) 662-665.  
  24. Z.-L. Chen, Scheduling and common due date assignment with earliness and tardiness penalties and batch delivery costs. Eur. J. Oper. Res.93 (1996) 49-60.  
  25. T. Cheng and Z.-L. Chen, Parallel-machine scheduling problems with earliness and tardiness penalties. J. Oper. Res. Soc.45 (1994) 685-695.  
  26. R. Daniels and R. Chambers, Multiobjective flow-shop scheduling. Naval Res. Logist.37 (1990) 981-995.  
  27. P. Dileepan and T. Sen, Bicriterion static scheduling research for a single machine. Omega16 (1998) 53-59.  
  28. P. Dileepan and T. Sen, Bicriterion jobshop scheduling with total flowtime and sum of squared lateness. Engrg. Costs and Production Economics21 (1991) 295-299.  
  29. M. Ehrgott, Multiple Criteria Optimization: Classification and Methodology, Ph.D. Thesis. University of Kaiserslautern, Germany, in English (1997).  
  30. H. Emmons, A note on a scheduling problem with dual criteria. Naval Res. Logist. Quarterly22 (1975) 615-616.  
  31. H. Emmons, One machine sequencing to minimize mean flow time with minimum number tardy. Naval Res. Logist. Quarterly22 (1975) 585-592.  
  32. H. Emmons, Scheduling to a common due date on parallel uniform processors. Naval Res. Logist.34 (1987) 803-810.  
  33. G. Evans, An overview of techniques for solving multiobjective mathematical programs. Management Sci.30 (1984) 1268-1282.  
  34. T. Fry, R. Armstrong and R. Blackstone, Minimizing weighted absolute deviation in single machine scheduling. IEEE Trans.19 (1987) 445-450.  
  35. T. Fry, R. Armstrong and H. Lewis, A framework for single machine multiple objective sequencing research. Omega17 (1989) 595-607.  
  36. T. Fry and R. Blackstone, Planning for idle time: A rationale for underutilization of capacity. Int. J. Prod. Res.26 (1988) 1853-1859.  
  37. T. Fry and G. Leong, Bi-criterion single-machine scheduling with forbidden early shipments. Engrg. Costs and Production Sci.10 (1986) 133-137.  
  38. T. Fry and G. Leong, A bi-criterion approach to minimizing inventory costs on a single machine when early shipments are forbidden. Comput. Operat. Res.14 (1987) 363-368.  
  39. T. Fry, G. Leong and T. Rakes, Single machine scheduling: A comparison of two solution procedures. Omega15 (1987) 277-282.  
  40. R. Gangadharan and C. Rajendran, A simulated annealing heuristic for scheduling in a flowshop with bicriteria. Comput. Industrial Engrg.27 (1994) 473-476.  
  41. M. Garey, R. Tarjan and G. Wilfong, One-processor scheduling with symmetric earliness and tardiness penalties. Math. Oper. Res.13 (1988) 330-348.  
  42. F. Gembicki, Vector Optimization for Control with Performance and Parameter Sensitivity Indices, Ph.D. Thesis. Case Western Reserve University, Cleveland, USA (1973).  
  43. A. Geoffrion, Proper efficiency and the theory of vector maximization. J. Math. Anal. Appl.22 (1968) 618-630.  
  44. J. Gupta, J. Ho and A. VanderVeen, Single machine hierarchical scheduling with customer orders and multiple job classes. Ann. Oper. Res.70 (1997) 127-143.  
  45. J. Gupta, V. Neppalli and F. Werner, Minimizing total flow time in a two-machine flowshop problem with minimum makespan. Internat. J. Production Economics (to appear).  
  46. S. Gupta and T. Sen, Minimizing a quadratic function of job lateness on a single machine. Engrg. Costs and Production Economic7 (1983) 187-194.  
  47. Y. Haimes, L. Ladson and D. Wismer, On a bicriterion formulation of the problems of integrated system identification and system optimization. IEEE Trans. Systems, Man and Cybernetics1 (1971) 296-297.  
  48. H. Heck and S. Roberts, A note on the extension of a result on scheduling with secondary criteria. Naval Res. Logist. Quarterly19 (1972) 4.  
  49. J. Hoogeveen, Single-Machine Bicriteria Scheduling, Ph.D. Thesis. CWI Amsterdam (1992).  
  50. J. Hoogeveen and S. VandeVelde, Minimizing total completion time and maximum cost simultaneously is solvable in polynomial time. Oper. Res. Lett.17 (1995) 205-208.  
  51. T. John, Tradeoff solutions in single machine production scheduling for minimizing flow time and maximum penalty. Comput. Oper. Res.16 (1984) 471-479.  
  52. J. Kanet, Minimizing the average deviation of job completion times about a common due date. Naval Res. Logist. Quarterly28 (1981) 643-651.  
  53. S. Kondakci, E. Emre and M. Koksalan, Scheduling of unit processing time jobs on a single machine, edited by G. Fandel and T. Gal, Multiple Criteria Decision Making. Springer-Verlag, Lecture Notes in Econom. and Math. Systems (1997) 654-660.  
  54. C. Koulamas, Single-machine scheduling with time windows and earliness/tardiness penalties. Eur. J. Oper. Res.91 (1996) 190-202.  
  55. S. Lakshminarayan, R. Lakshmanan, R. Papineau and R. Rochette, Optimal single-machine scheduling with earliness and tardiness penalties. Oper. Res.26 (1978) 1079-1082.  
  56. C.-Y. Lee and G. Vairaktarakis, Complexity of single machine hierarchical scheduling: A survey, edited by P.M. Pardalos, Complexity in Numerical Optimization. World Scientific Publishing Co. (1993) 269-298.  
  57. J.-T. Leung and G. Young, Minimizing schedule length subject to minimum flow time. SIAM J. Comput.18 (1989) 314-326.  
  58. C.-L. Li and T. Cheng, The parallel machine min-max weighted absolute lateness scheduling problem. Naval Res. Logist.41 (1994) 33-46.  
  59. C.-J. Liao, W.-C. Yu and C.-B. Joe, Bicriterion scheduling in the two-machine flowshop. J. Oper. Res. Soc.48 (1997) 929-935.  
  60. K. Lin, Hybrid algorithm for sequencing with bicriteria. J. Opt. Theor. Appl.39 (1983) 105-124.  
  61. S. McCormick and M. Pinedo, Scheduling n independant jobs on m uniform machines with both flowtime and makespan objectives: A parametric analysis. ORSA J. Comput.7 (1995) 63-77.  
  62. K. Miettinen. On the Methodology of Multiobjective Optimization with Applications, Ph.D. Thesis. University of Jyvaskyla, Department of Mathematics (1994).  
  63. S. Miyazaki, One machine scheduling problem with dual criteria. J. Oper. Res. Soc. Jpn.24 (1981) 37-50.  
  64. A. Nagar, J. Haddock and S. Heragu, Multiple and bicriteria scheduling: A literature survey. Eur. J. Oper. Res. (1995) 88-104.  
  65. A. Nagar, S. Heragu and J. Haddock, A branch-and-bound approach for a two-machine flowshop scheduling problem. J. Oper. Res. Soc.46 (1995) 721-734.  
  66. R. Nelson, R. Sarin and R. Daniels, Scheduling with multiple performance measures: The one-machine case. Management Sci.32 (1986) 464-479.  
  67. V. Neppalli, C.-L. Chen and J. Gupta, Genetic algorithms for the two-stage bicriteria flowshop problem. Eur. J. Oper. Res.95 (1996) 356-373.  
  68. P. Ow and T. Morton, Filtered beam search in scheduling. Internat. J. Production Res.26 (1988) 35-62.  
  69. P. Ow and T. Morton, The single machine early/tardy problem. Management Sci.35 (1989) 177-190.  
  70. S. Panwalker, M. Smith and A. Seidmann, Common due date assignment to minimize total penalty for the one machine scheduling problem. Oper. Res.30 (1982) 391-399.  
  71. C. Rajendran, Two-stage flowshop scheduling problem with bicriteria. J. Oper. Res. Soc.43 (1992) 871-884.  
  72. C. Rajendran, A heuristic for scheduling in flowshop and flowline-based manufacturing cell with multi-criteria. Internat. J. Production Res.32 (1994) 2541-2558.  
  73. C. Rajendran, Heuristics for scheduling in flowshop with multiple objectives. Eur. J. Oper. Res.82 (1995) 540-555.  
  74. F. Riane, N. Meskens and A. Artiba, Bicriteria scheduling hybrid flowshop problems, in International Conference on Industrial Engineering and Production Managment (IEPM'97). Lyon, France (1997) 34-43.  
  75. B. Roy, Méthodologie multicritère d'aide à la décision. Economica (1985).  
  76. S. Sayin and S. Karabati, A bicriteria approach to the two-machine flow shop scheduling problem. Eur. J. Oper. Res.113 (1999) 435-449.  
  77. A. Seidmann, S. Panwalker and M. Smith, Optimal assignment of due-dates for a single processor scheduling problem. Internat. J. Production Res.19 (1981) 393-399.  
  78. W. Selen and D. Hott, A mixed integer goal-programming formulation of a flowshop scheduling problem. J. Oper. Res. Soc.37 (1986) 1121-1128.  
  79. T. Sen and S. Gupta, A branch-and-bound procedure to solve a bicriterion scheduling problem. IEEE Trans.15 (1983) 84-88.  
  80. T. Sen, F. Raiszadeh and P. Dileepan, A branch-and-bound approach to the bicriterion scheduling problem involving total flowtime and range of lateness. Management Sci.34 (1988) 255-260.  
  81. F. Serifoglu and G. Ulusoy, A bicriteria two-machine permutation flowshop problem. Eur. J. Oper. Res.107 (1998) 414-430.  
  82. J. Shantikumar, Scheduling n jobs on one machine to minimize the maxium tardiness with minimum number tardy. Comput. Oper. Res.10 (1983) 255-266.  
  83. J. Sidney, Optimal single-machine scheduling with earliness and tardiness penalties. Oper. Res.25 (1977) 62-69.  
  84. W. Smith, Various optimizers for single-stage production. Naval Res. Logist. Quarterly3 (1956) 59-66.  
  85. R. Soland, Multicriteria optimization: A general characterization of efficient solutions. Decision Sci.10 (1979) 27-38.  
  86. R. Steuer, Multiple criteria optimization: Theory, computation and application. Wiley (1986).  
  87. P. Sundararaghavan and M. Ahmed, Minimizing the sum of absolute lateness in single-machine and multimachine scheduling. Naval Res. Logist. Quarterly31 (1984) 325-333.  
  88. W. Szwarc, Single-machine scheduling to minimize absolute deviation of completion times from a common due date. Naval Res. Logist.36 (1989) 663-673.  
  89. V. T'kindt and J.-C. Billaut, L'ordonnancement multicritère. Presses de l'Université de Tours (2000).  
  90. V. T'kindt, J.-C. Billaut and H. Houngbossa, A multi-criteria heuristic to solve a 2-stage hybrid flowshop scheduling problem. Eur. J. Automation (JESA)34 (2000) 1187-1200.  
  91. V. T'kindt, J.-C. Billaut, S. Laurin and O. Meslet, Un algorithme optimal polynomial pour résoudre un problème d'ordonnancement bicritère à machines parallèles, in Conference on Automation-Computers Engineering-Image-Signal (AGIS'97). Angers, France (1997) 179-184.  
  92. V. T'kindt, J.-C. Billaut and C. Proust, Solving a bicriteria scheduling problem on unrelated parallel machines occuring in the glass bottle industry. Eur. J. Oper. Res.135 (2001) 42-49.  
  93. V. T'kindt, P. Richard, C. Proust and J.-C. Billaut, Resolution of a 2-machine bicriteria flowshop scheduling problem, in Int. Conference on Methods and Applications of Multicriteria Decision Making (MAMDM'97). Mons, Belgium (1997) 139-143.  
  94. M. VandenAkker, H. Hoogeveen and S. VandeVelde, in 6th International Workshop on Project Management and Scheduling (PMS'98). Istanbul, Turkey (1998).  
  95. L. VanWassenhove and K. Baker, A bicriterion approach to time/cost trade-offs in sequencing. Eur. J. Oper. Res.11 (1982) 48-54.  
  96. L. VanWassenhove and L. Gelders, Four solution techniques for a general one machine scheduling problem: A comparative study. Eur. J. Oper. Res.2 (1978) 281-290.  
  97. L. VanWassenhove and L. Gelders, Solving a bicriterion scheduling problem. Eur. J. Oper. Res.4 (1980) 42-48.  
  98. R. Vickson, Choosing the job sequence and processing times to minimize total processing plus flow cost on a single machine. Oper. Res.28 (1980) 115-167.  
  99. R. Vickson, Two single machine sequencing problems involving controllable job processing times. IEEE Trans.12 (1980) 158-162.  
  100. A. Vignier, J.-C. Billaut and C. Proust, Solving k-stage hybrid flowshop scheduling problems, in Multiconference on Computational Engineering in Systems Applications (CESA'96), Symposium on Discrete Events and Manufacturing Systems (IEEE-SMC/IMACS). Lille, France (1996) 250-258.  
  101. A. Vignier, J.-C. Billaut and C. Proust, Les flowshop hybrides : état de l'art. RAIRO: Oper. Res.33 (1999) 117-183.  
  102. S. Webster, P. Job and A. Gupta, A genetic algorithm for scheduling job families on a single machine with arbitrary earliness/tardiness penalties and an unrestricted common due date. Internat. J. Production Res.36 (1998) 2543-2551.  
  103. A. Wierzbicki, The use of reference objectives in multiobjective optimization, edited by G. Fandel and T. Gal, Multiple criteria decision making, theory and application. Springer-Verlag (1990) 468-486.  
  104. J. Wilson, Alternative formulations of a flow-shop scheduling problem. J. Oper. Res. Soc.40 (1989) 395-399.  
  105. S. Zegordi, K. Itoh and T. Enkawa, A knowledgeable simulated annealing scheme for the early/tardy flow shop scheduling problem. Internat. J. Production Res.33 (1995) 1449-1466.  

NotesEmbed ?

top

You must be logged in to post comments.

To embed these notes on your page include the following JavaScript code on your page where you want the notes to appear.

Only the controls for the widget will be shown in your chosen language. Notes will be shown in their authored language.

Tells the widget how many notes to show per page. You can cycle through additional notes using the next and previous controls.

    
                

Note: Best practice suggests putting the JavaScript code just before the closing </body> tag.